Philips Street bridge timing


philip st bridge

Maurice Goulet, DPW Director, sent a resident an email update today on the timing of the Philips Street bridge repair (a copy of the email appears below) –

==============================================================

The RFP has been sent out to prospective bidders. Within 2-3 weeks we should have a fabricator selected and begin the manufacturing of the deck. The final repairs of the bridge will be determined by the winter weather and the awarding contractor availability at the time coordination is setup with the delivery of the pre-fabricated bridge.

==============================================================

We were previously told that the fabrication will take about 16 weeks.

Based on information and belief, there is some concern that once the bridge work is completed, that bridge abutter Alec Stevens may not cede back to the town his basketball court (f/k/a Philips Street).

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s