Category Archives: Medfield State Hospital

State OK’s DCAM’s Change to the Clean Up

This is a copy of the Secretary of Energy and Environmental Affairs’ approval of the change in the MSH clean up

=============================================

August 10, 2011
CERTIFICATE OF THE SECRETARY OF ENERGY AND ENVIRONMENTAL AFFAIRS
ON THE NOTICE OF PROJECT CHANGE

PROJECT NAME : Medfield State Hospital Cleanup and Redevelopment PROJECT MUNICIPALITY : Medfield PROJECT WATERSHED : Charles River EOEANUMBER : 14448R PROJECT PROPONENT : Massachusetts Division of Capital Asset Management
(DC AM) DATE NOTICED IN MONITOR : June 22, 2011

Pursuant to the Massachusetts Environmental Policy Act (MEPA) (M.G.L. c.30, ss. 61621) and Section 11.10 of the MEPA regulations (301 CMR 11.00), I have reviewed the Notice of Project Change (NPC) describing the selection and implementation of an Immediate Response Action (IRA) cleanup option for the Construction and Debris (C&D) Area and adjacent portions of the Charles River at the Medfield State Hospital (MSH) and hereby determine that this phase ofthe project does not require the preparation of an Environmental Impact Report (EIR). However, in accordance with the Certificate dated April 2, 2010, the project as a whole continues to require the preparation of a Single EIR (SEIR) that will address the cumulative impacts of all phases ofthe project. In a separate Draft Record of Decision (DROD) also being issued today, I am proposing to grant a Phase 1 Waiver, allowing these cleanup activities in the C&D Area and adjacent Charles River to proceed in advance of the SEIR for the project, subject to public comment. If the Phase 1 Waiver is not granted, then I will reissue this Certificate on the NPC with a denial of the requested Phase 1 Waiver. Although I have not issued a new scope for the SEIR based on the NPC, the SEIR should incorporate impacts from Phase 1, as well as an assessment ofthe project’s cumulative impacts.

Project History
In 2010, the Proponent, DCAM, submitted an Expanded Environmental Notification Form (EENF) proposing the cleanup and redevelopment of the MSH in Medfield. The proposed project presented in the EENF consists of remediation and redevelopment ofthe 269-acre former
EEA #14448R NPC Certificate August 10,2011
MSH site. MSH was originally developed in the late 19th century as a residential hospital for the mentally ill. The hospital was closed in 2003 and its control was transferred to DCAM. DCAM proposes first to conduct a cleanup ofdebris at five sites, and, under the provisions of the Massachusetts Contingency Plan (MCP), to remediate hazardous waste at three sites. Redevelopment is then planned for the 94.2-acre central portion of the campus once cleanup measures are complete. The site was previously developed and contains approximately 50 buildings totaling 788,000 square feet (sf) of building space. The Redevelopment will be guided by the MSH Reuse Plan, authorized by the Legislature through special legislation passed in 2008, and includes rehabilitation of the Campus and the construction of several new buildings to provide 440 dwelling units and approximately 41,000 sf of office and community center space.

DCAM anticipates transferring the Redevelopment portion of the site (134 acres) to a third party through a public bidding process, and approximately 60 acres of that area (comprised ofthe hospital tubular well fields, Sledding Hill, and the hospital water tower and access easement) will be transferred to the Town of Medfield. Approximately 114.8 acres of the site will remain with the Commonwealth, with portions to be transferred among four Commonwealth agencies. The Department of Conservation and Recreation (DCR) will receive control of73.3 acres that form a horseshoe around the Redevelopment parcel, as well as a six-acre parcel located between a rail line and Route 27. A 2.5-acre parcel will be retained by the Department of Developmental Services (DDS) for a group home. Another 30.3 acres of the site (former sewage beds) will be transferred to the Executive Office of Public Safety (EOPS) for the continued use of public safety agencies as a firearms practice range. Finally, the 2.7-acre hospital cemetery will be retained by the Department of Mental Health (DMH).

As noted above, portions of the site are contaminated from past activities related to operation of the state hospital. These areas will be remediated in compliance with the MCP before transfer of the property is executed. DCAM been granted a Special Project Designation (SPD) Permit in accordance with 310 CMR 40.0060 for the three MCP-regulated sites in order to coordinate public involvement and remediation. In addition to the obligations of remediation, the disposal sites included within the SPD Permit have also been designated as Public Involvement Plan (PIP) sites. As PIP sites, DCAM is responsible for communication of assessment and remedial activities associated with the disposal sites and for providing opportunities for public involvement and comment throughout the MCP process. Because ofthe SPD Permit and the PIP designation, there will be substantial oversight of cleanup activities by MassDEP.
Anticipated environmental impacts associated with the entire project include approximately 7.2 acres of new land alteration, 2.3 acres of new impervious area, 2,700 new average daily trips (adt), 115 new parking spaces, and approximately 93,400 gallons per day (GPD) of new water usage and 84,900 GPD of new wastewater generation. The project also includes the construction of new water and sewer mains onsite. Wetlands impacts associated with the project include the temporary alteration of 500 linear feet (If) of Bank, 2,500 sf of Bordering Vegetated Wetland (BVW), and 43,700 sf of Riverfront Area associated with the remediation. The project also involves the demolition of state-listed historic and/or archaeological resources.
On April 2, 2010, Secretary Ian A. Bowles issued a Certificate on the EENF requiring an
2
EEA #14448R NPC Certificate August 10, 2011

EIR for the entire project. In the Certificate, the Secretary allowed DCAM toproceed with the cleanup and remediation ofthose hazardous waste sites that will not impact wetland resource areas (both those regulated under the MCP and otherwise), prior to the submission of the SEIR for the entire project.

Summary ofProject Change (Phase 1)

As described in the NPC, the project change consists of the selection and implementation of an IRA cleanup option for the C&D Area and adjacent portions ofthe Charles River at the MSH site in advance ofthe preparation of the SEIR. According to DCAM1, the discovery of an oily sheen in the Charles River during removal of sampling equipment in May 2011 created a condition of Substantial Release Migration (SRM) under the MCP. This condition of SRM warrants the implementation of an IRA by DCAM to resolve the condition.

A Notice of Intent was included in the NPC, and includes tables entitled “Initial Remedial Alternatives Technology Screening”, for both the C&D Area and the sediments in the Charles River, respectively, in which DCAM provides a comparison of several preliminary alternatives. DCAM’s selected remedial approach will include: bank stabilization and cover of the C&D Area; and the construction of a temporary sediment cap within the adjacent Charles River. The NPC does not propose changes to the majority ofthe project as originally reviewed in the EENF. The remediation of both MCP and non-MCP sites is ongoing and the status of cleanup efforts is detailed in the appended Draft Phase II Report and the Non-MCP Area Report, respectively. The NPC indicates that a fourth disposal area -the Clay Contairunent Area (a historically non-MCP site) is now included in the SPD Permit (in addition to the Salvage Yard Area, the Former Power Plant Area, and the C&D Area).

According to the NPC and comments from DCAM1, the project change consists of:
• bank stabilization, excavation, and cover of C&D Area including:
removal ofthe existing steep slopes by cutting back debris material to a more stable 3: 1 slope;
-lowering the elevation of the C&D Area by an additional three feet below the proposed final grade, installing a 40 mil textured high density polyethylene (HDPE) liner and marker barriers, and overlaying three feet of clean fill to bring the site up to the final grade (along the Algonquin Gas easement which runs through the C&D Area, the three-foot cover will be reduced to one-foot over an HDPE liner);
-removal of approximately 11,000 tons of contaminated material;
-installing a riprap toe at base ofthe slope with riprap extending up to the Ordinary High Water Line (OHW);
-an increase in size of the C&D Area from 2.2 acres to 3.2 acres;

1 As described in DeAM’s comment letter dated August 8, 2011.

3

EEA #14448R NPC Certificate August 10, 2011

– work to stabilize the C&D Area will temporarily affect:
•  780 If of Bank (increase of 280 If from EENF),
•  3,750 sq ofBVW (increase of 1,250 sf from EENF),
•  104,500 sf of Riverfront Area (increase of 60,800 sf from EENF),
•  8,560 sf of Land Under Water (LUW), and
•  2,400 cubic yards (CY) of Bordering Land Subject to Flooding (BLSF), with a net 50 CY of flood storage gained;
-restoration of Bank, LUW, and Riverfront Areas, and wetland replication of 5,150 sf ofBVW (net gain of 1,400 sf);
-removal of a net 770 CY of dredged material (1,420 CY of material will be dredged from below OHW line to overcut the bank to allow for the placement of 620 CY of riprap and clean fill; an additional 30 CY will be placed in order to remediate the contaminated sediment)
– bio-stabilization of the slope above the OHW employing the brush layering technique to protect the slope from erosion and to provide a more natural habitat;
• emplacement of a temporary sediment cap including:
-covering an approximate area of 800 sf of impacted sediment (within the top 6-12 inches) within the Charles River with an impermeable amendment material (AquaBlok -a “composite particle technology”) to provide a low permeability, in situ active cover which is intended to create a barrier to isolate impacted sediment and impede potential upward and downstream migration into the river;
12 inches of fill throughout the impacted sediment area (six inches of AquaBlok overlain by six inches of sand);
– work to cover the sediments will temporarily result in 30 CY of fill to LUW (15 CY of clean fill and 15 CY of AquaBlok).
DC AM has requested that I allow the implementation of the IRA cleanup option to proceed prior to the submission of the SEIR. According to DCAM, delaying the remediation activities until the SEIR has been completed may adversely affect the Charles River and the C&D Area because the current unstabilized condition of SRM could result in further impacts to the Charles River. In addition, DCAM indicates that it anticipates the filing of a subsequent NPC to the MEP A Office which details the determination of the final remedial actions. I have therefore issued a DROD detailing my proposal to grant the Phase I Waiver. If approved under the proposed Waiver, DCAM will endeavor to complete the temporary cleanup activities in fall 2011.
4

EEA #14448R NPC Certificate August 10,2011

MEPA Jurisdiction and Permits

The project, as presented in the EENF, is not subject to a mandatory EIR based upon the MEPA regulations. However, due to the potential environmental impacts of the project, and the unique nature of the project site, the preparation of an EIR was required.
The project is undergoing review pursuant to Sections 11.03(3)(b)(1)(b), 11.03(3)(b)(1)(f), 11.03(6)(b)(13), and 11.03(10)(b)(1) of the MEPA regulations because it is being undertaken by a State Agency and will result in the alteration of 500 or more linear feet of inland bank, the alteration of one-half or more acres of other wetlands (Riverfront Area), the generation of 2,000 or more new adt on roadways providing access to a single location, and the demolition of a Historic Structure listed in or located in any Historic District listed in the State Register of Historic Places. The project will require: an Order of Conditions from the Medfield Conservation Commission (and, on appeal only, a Superseding Order of Conditions from the Massachusetts Department of Environmental Protection (MassDEP)); a Sewer Connection Permit from MassDEP; review by the Natural Heritage and Endangered Species Program (NHESP); review by the Massachusetts Historical Commission (MHC); and a National Pollutant Discharge Elimination System (NPDES) Construction General Permit (CGP) from the United States Environmental Protection Agency (US EPA). The project could potentially also require air quality approvals from MassDEP if it proposes installation of boilers, furnaces or emergency generators. The project is also subject to the EEAlMEPA Greenhouse Gas Emissions Policy and Protocol.

The project change (Phase 1) will require: an Order of Conditions from the Medfield Conservation Commission (and, on appeal only, a Superseding Order of Conditions from MassDEP); a Section 401 Water Quality Certificate from MassDEP; and a Category 2 Programmatic General Permit from the United States Army Corps of Engineers (ACOE). The project will also require review in accordance with the MCP by MassDEP, including, but not limited to, a Phase II Comprehensive Site Assessment (CSA) and a Phase III Remedial Action Plan (RAP).

The project will be undertaken and financed by DCAM, a State Agency. In addition, the project involves a Land Transfer from DCAM. Therefore, MEP A jurisdiction for this project is broad and extends to all aspects of the project that are likely, directly or indirectly, to cause Damage to the Environment, as defined in the MEPA regulations.

REVIEW OF THE NPC

The NPC provides a description of proposed Phase 1 activities and a discussion of their associated environmental impacts including mitigation and responsibilities under the MCP. According to DCAM2, it has elected to proceed with covering the contaminated sediment as a temporary solution until such time as a comprehensive study can be developed for the final remedy that discusses dredging options. As indicated in the comments from MassDEP’s Bureau
2 As described in DCAM’s comment letter dated August 8, 2011.
5

EEA #14448R NPC Certificate August 10, 2011

of Waste Site Cleanup (BWSC), DCAM will be required to submit a focused Phase III feasibility evaluation to MassDEP by August 10, 2011 prior to implementing the IRA Plan. The MCP does not allow the construction of a cap as part of a Permanent Solution unless a Phase III feasibility evaluation is completed. Although DCAM has indicated that the capping would be temporary, it acknowledges that the potential exists that the remediation proposed may be determined the most feasible, and therefore, the long-term Permanent Solution. I note that the Town ofMedfield Board of Selectmen (BOS) comments discuss requirements under the MCP which require than an IRA shall not, to the extent practicable, prevent or impede the implementation of future response actions.

In addition, MassDEP will conduct a technical meeting in the near future with DCAM and stakeholders including, but not limited, to representatives from the State Hospital Environmental Review Committee (SHERC) and PIP petitioners following submission of the Phase III feasibility evaluation. During this meeting, I ask DCAM and MassDEP to consider the remedial alternatives suggested by CRWA and the Town of Medfield BOS as Permanent Solutions in their comment letters. Specifically, DCAM should explain the rationale for scoring of the remedial alternatives in the tables entitled “Initial Remedial Alternatives Technology Screening” .

As described in the NPC, DCAM has designed the Phase 1 project to address a condition of SRM within the Charles River and minimize adverse impacts to the environment. Comments received from MassDEP’s BWSC indicate that upon resolution of the technical issues, it expects that the IRA will be performed this construction season while low water levels in the Charles River prevail. I encourage DCAM to continue to work with MassDEP to ensure that impacts to resource areas are avoided and minimized to the maximum extent feasible, and that appropriate mitigation is provided.

I acknowledge the concerns expressed by the Charles River Watershed Association (CR W A) regarding potential environmental impacts as a result of not dredging or removing the contaminated material onsite. I also note that DCAM’s consultants provided a letter, dated August 8, 2011, in response to these comments addressing several of the key topics raised. Although I am declining to require the preparation of a supplemental EIR because MassDEP can address any outstanding issues during project permitting, DCAM should continue to work closely with the state permitting agencies and stakeholders to ensure that the impacts ofthe project are avoided, minimized and mitigated to the maximum extent feasible.

Comments from CRWA and the Town of Medfield BOS note that the placement ofa cap . may prohibit other alternatives from later being employed due to physical and financial impediments. DCAM indicates that only a small volume of AquaBlok will be required for the temporary measure, and if it is required, the AquaBlok can be removed easily via either hydraulic or mechanical dredging.

Comments from the Town of Medfield BOS voice strong concern regarding the remediation of the Charles River and C&D Area and its potential impact on the Town’s principal public water supply well #6, and the area considered a potentially productive aquifer. DCAM should ensure that any remedial alternative employed takes into consideration the environmental
6

EEA #14448R NPC Certificate August 10, 2011

sensitivity ofthis area as a drinking water supply.

I note CRWA’s comments regarding its concerns with the reuse of clean concrete. DCAM has indicated that although it has reused clean concrete on other MCP sites with the encouragement of MassDEP, the reference in the NPC which states that onsite concrete will reused as riprap is erroneous. The crushed concrete at the C&D Area cannot be used as riprap due to concerns about it durability under scour conditions. I also note that DCAM indicates that the reference, by CRW A, to mercury being a contaminant ofconcern is incorrect.

I expect DCAM will develop a comprehensive Monitoring and Response Plan, including an Emergency Flood Response Plan, as recommended by CRWA, if monitoring shows contaminant levels above reportable concentrations or ifhigh intensity rain events are predicted.

On April 19, 2010, the NHESP issued a determination letter regarding the review ofthe project under the Massachusetts Endangered Species Act (MESA) and its implementing regulations which indicates that the recent changes outlined in the NPC do not result in changes in its previous determination that project will not result in a prohibited “take” of state-listed species andior additional requirements.

In its comment letter on the NPC, MassDEP has stated that DCAM should be aware that the Town ofMedfield is working on Infiltration and Inflow (III) problems within its municipal sewers but that there continues to be significant amounts ofIII that must be addressed as part of any new sewer connection. DCAM should not construct any new sewers until after the Town has completed the upgrades to its aging Publicly Owned Treatment Works (POTW) for which plans are underway.

The SEIR should continue to respond to the Scope set forth in the Certificate on the EENF issued on April 2, 2010. It should also present revised analyses to incorporate the changes to the project presented in the NPC, and should contain a full analysis ofthe cumulative impacts ofthe entire project, including impacts associated with Phase 1.

Summary of Proposed Mitigation Measures

According to the NPC, DCAM will mitigate the impacts to wetland resource areas by replicating the majority ofwetland impacts in place. Restoration volumes are described in Table 2 below (reproduced from the NPC):
7

EEA #14448R NPC Certificate August 10,2011

Table 2: Resource Area Mitigation
Resource Area
Impacted
Unit
Restored
Net Change
BVW
3,750
sf
5,150
+1,400
LUW (Below OHW)
8,560
sf
8,560
0
LUW Dredge
1,420
CY
770 CY Dredge
LUW Fill
650
CY
BLSF Cut
2,450
CY
50 CY of Storage Added
BLSF Fill
2,400
CY
Riverfront Area
104,500
sf
104,500
0
Bank
780
If
780
0

Waiver Request

As noted above and as set forth more fully in the DROD also being issued today, DCAM has requested a Phase 1 Waiver to allow IRA cleanup activities of the C&D Area and adjacent Charles River to proceed in advance of completion of the SEIR. DCAM anticipates that a subsequent NPC will be submitted to the MEP A Office once the final remediation actions are determined.3 This NPC, slated for submission in early 2012, will either document that the temporary solution is suitable as a permanent solution or provide a complete analysis of the permanent solution resulting from the Phase III RAP. In addition to the PIP process, this future NPC will provide another forum for public comment on DCAM’s approach to achieving a condition of “No Significant Risk” as defined in the MCP for the MSH site. The future NPC should also provide detailed responses to the comments submitted on this current NPC. Based upon my review of the NPC and the comments received, I propose to grant the Phase 1 Waiver, in the DROD, which will be noticed for public comment. The DROD contains conditions and supplemental information to be submitted to the MEP A Office to ensure that the impacts from Phase 1 are avoided, minimized, and mitigated to the maximum extent feasible. In addition, the cumulative impacts of the project should be further addressed in the SEIR.

I acknowledge the comments and concerns expressed by CRWA, and the Town of Medfield BOS and residents about the impacts of Phase 1 and requesting that the project be required to prepare an EIR prior to conducting IRA activities. While I appreciate the concerns expressed in the letters, I do not believe that the impacts of Phase 1 warrant the preparation of an EIR under the applicable provisions of the MEPA regulations which I am required to apply. DCAM has indicated that the proposed Phase 1 activities are of a temporary nature to resolve the condition of SRM and that a detailed analysis of all remedial alternatives for the contamination will be presented in the Phase III RAP, which will be presented initially to the PIP group in September 2011. I am also confident that the cumulative impacts of the project can be fully reviewed in the context of the SEIR. I expect that DCAM will provide detailed responses to these comments in both the future NPC and the SEIR and continue to work with stakeholders to address their ongoing concerns.
3 As described in DCAM’s comment letter dated August 8, 2011. 8

EEA #14448R NPC Certificate August 10,2011

Conclusion

Based upon a review of comments letters, and after consultation with the relevant state agencies, I am confident that MassDEP has sufficient permitting authority to condition Phase 1 of the project so that no significant environmental impacts occur. I have proposed in a separate DROD issued today to grant a Phase 1 Waiver for IRA cleanup activities at the C&D Area and adjacent Charles River. Further MEPA review continues to be required for the entire project in the SEIR. The impacts from Phase 1 should be incorporated into the assessment of overall impacts for the project in the SEIR.
August 10,2011
DATE

/s/ Maeve Vallely Bartlett,for Richard K Sullivan, Jr.
Comments received:
07/1312011 Natural Heritage and Endangered Species Program
08/03/2011 Charles River Watershed Association
0810312011 Town of Medfield Board of Selectman
08/0412011 William J. Massaro
08/05/2011 Massachusetts Department of Environmental Protection -CERO
08/0512011 Massachusetts Department of Environmental Protection -CEROBureau of Waste Site Cleanup
08/0812011 Massachusetts Division of Capital Asset Management

RKS/PPP/ppp
9

DCAM’s Quirky Chronology

DCAM filed a notice of intent with the Town of Medfield Conservation Commission (ConCom) this past June to do what it then called permanent remediation the C&D area at the Medfield State Hospital.  The general plan then was to pull the contaminated materials away from the edge of the river bank in places they form an almost vertical embankment, create a more gradual sloped bank in to the river, and cap the contaminated materials on the site.

However, then in July an oil sheen was seen when DCAM’s engineers were boring test holes in what we now know to be about 800 sq. ft. of oil underwater in the Charles River, and that oil sheen triggered what the state regulations call an Immediate Response Action (IRA).  Atfer that point the Massachusetts DEP was telling DCAM that because of that oil sheen, an IRA required that something needed to be done this construction season.  However, note that DCAM was already trying to do something this construction season.  Now in August DCAM is still asking the ConCom for the same permit to do the work originally requested in June, but now it is under the rubric of the IRA and only temporary work, made necessary by the oil sheen, and includes the temporary capping of the oil in the river.

The unfortunate reality is that DCAM’s Phase II and Phase III reports that will delineate the totality of the problems and the complete solutions they propose are due out this month.  Where those final documents are due so soon, it would make much more sense for DCAM to allow everyone to see those documents before it does any more work at the Medfield State Hospital.

The Town’s fear is be that DCAM’s proposed temporary fix will become the de facto permanent fix because of cost issues (it may be argued later that it makes no sense financially to spend money to remove the temporary fix), despite what we may learn from the Phase II and Phase III reports.  The Medfield Board of Selectmen wrote t DCAM on 8/1/11 to ask that the oil all be removed from the river, rather than just temporarily put a cap over it as DCAM proposes, as removal is a more logical, long term,  permanent fix of the problem of the oil in the Charles River – oil caused to be in the river by the state acts.

DCAM will Report of Salvage Area Clean Up, Thursday at 7PM

What follows is the letter to PIP group members from DCAM about the meeting it is holding this Thursday at 7 PM.

=======================================

August 5,2011

Medfield State Hospital PIP Group
Medfield, MA

RE:  PIP Meeting to Present the Draft RAM Completion Report and Partial RAO For the Salvage Yard Area Medfield State Hospital

Dear PIP Member:

The Division of Capital Asset Management (DCAM) is providing notice that a Public Involvement Plan (PIP) meeting will be held on Thursday, August uth , at 7pm at the Selectman’s Meeting Room at the Medfield Town House. The purpose of this meeting is to present the draft RAM Completion Report and Partial RAO for the Medfield State Hospital Salvage Yard Area.
If you wish to be removed from this mailing list, please notify me at DCAM via regular mail or email atallen.wiggin@state.ma.us

Sincerely,
Division of Capital Asset Management
Alan Wiggin, Pgr Coordinator
cc: Carole Cornelison, Commissioner, DCAM
John O’Donnell, Deputy Director, DCAM
Mary Beth Clancy, SR. Program Mgr., DCAM
Mark Baldi, Mass DEP-CERO
Michael Sullivan, Medfield Town Administrator
Medfield Public Library Repository
Frank Ricciardi, Weston & Sampson

MSH Conundrum

DCAM is responding to DEP over its stated need for DCAM to clean up on an emergency basis about 800 sq. ft. of oil found in the Charles River when DCAM drilled test holes, but DEP has told DCAM that it cannot proceed until it both first completes a feasibility study and also meets with the Town’s SHERC later this month.  It is a conundrum because last night before the Town of Medfield Conservation Committee, DCAM was forging ahead to get permission to do the work to cap the oil in the river with a product called Aquablok and to pull back from the river and to cap the adjoining C&D area,despite not having yet met with SHERC and DEP or completed the feasibility study.

DEP is telling DCAM that they need to respond to the oil in the river this construction season, so DCAM is doing what it must to forge ahead, despite not yet really knowing which way it will ultimately be going.  The ConCom did vote last night, on a split vote, approval of the Notice of Intent from DCAM for the proposed emergency temporary remediation work, which DCAM acknowledges that it cannot perform until it meets the above criteria set by DEP, and which work may or may not be the emergency fix and may or may not be the permanent fix.

SHERC’s chair met in a working meeting last Friday at my initiation with DCAM, and per DCAM last night may well have been able to resolve all the issues if only DEP had attended.

Medfield’s Board of Selectmen agreed at our last meeting with my position suggestion from our prior meeting to urge DEP and DCAM that (1) the oil in the river be removed instead of being capped, and (2) that a permanent solution for the river adjoining C&D area involve pulling out any materials below the groundwater table and capping those materials on site.  The C&D area is physically proximate to the town’s well #6, located near where Rte 27 crosses the Charles River, and the town must be vigilant about keeping the buried hazardous materials at the C&D area from ever polluting the aquifer that supplies that well.

DEP Tells DCAM to Hold Off & to Meet with Town Week of 8/22/11

DEP wrote this letter to DCAM today about the MSH clean plan and up timing.

COMMONWEALTH OF MASSACHUSETTS
EXECUTIVE OFFICE OF ENVIRONMENTAL AFFAIRS
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Central Regional Office, 627 Main Street, Worcester, MA 01608

Commonwealth of Massachusetts
Division of Capital Asset Management
One Ashbmton Place
Boston, MA 02108
Attention: John O’Donnell
Deputy Director
Re: CRWSC – Medfield
45 Hospital Road
FOlmer Medfield State Hospital
RTN 2-3020799
Immediate Response Action Plan
310 CMR40.0000
M.G.L. c.21E

Dear Mr. O’Donnell:

On July 20,2011, the Massachusetts Department of Environmental Protection (MassDEP) received a “Draft Immediate Response Action Plan” for the Construction and Demolition Area (the “C&D Area”) at the fOlmer Medfield State Hospital. The Immediate Response Action (IRA) Plan proposes excavating contaminated soil and debris, emplacing a temporary sediment cap within the
adjacent Charles River, and reconstructing the river bank to eliminate continued leaching and/or erosion of soil resulting in petroleum contamination of sediment that has is or likely to result in impacts to surface water as a condition of Substantial Release Migration (SRM).

Pursuant to 310 CMR 40.0414(7), the Massachusetts Contingency Plan does not allow construction of a cap 01′ engineered barrier as part of a Permanent Solution unless a Phase III feasibility evaluation is completed. As the river bank reconstruction with the proposed flexible membrane liner and riprap covel’, in addition to the use of the proposed Aquablock to isolate and contain contaminated sediment, may potentially be detelmined to be the most feasible  remedial altemative based on technology and cost-benefit considerations, it should be considered part of the Permanent Solution for the C&D area. A focused Phase III feasibility evaluation, focused on the C&D Area and river sediment, is necessary prior to implementing the IRA Plan. The submitted IRA Plan does not contain the equivalent of a Phase III feasibility evaluation, therefore, MassDEP requires a Phase III evaluation for the C&D Area to be submitted by August 10, 2011, the date of presumptive approval for the IRA Plan.
The IRA Plan shall not be considered presumptively approved with submittal of the Phase III feasibility evaluation. MassDEP reserves the right to approve the IRA after August 10,2011.  As a condition of approval MassDEP will require a technical meeting during the week of August

Page 2
22, 2011 or earlier, with the Division of Capital Asset Management, and select stakeholders including but not limited to representatives ofthe State Hospital Environmental Review Committee (SHERC) and Public Involvement Plan (PIP) petitioners following submittal of the feasibility evaluation. The purpose of the technical meeting will be to discuss and resolve technical issues with the IRA Plan scope of work. MassDEP will not provide approval of the IRA Plan prim’ to the technical meeting. Pending resolution oftechnical issues, it is MassDEP’s expectation that the IRA to eliminate and control the condition of SRM and its source will be perfOimed this constlUction season while low water levels of the Charles River prevail.
MassDEP appreciates the attention and cooperation of DC AM regarding these matters.  Please contact me with proposed dates and times for the technical meeting to be conducted the week of August 22 or earlier. If you have any questions, please contact me at (508) 767-2846.
August 5, 2011

Sincerely,

Mark E. Baldi
Section Chief, Audits
Bureau of Waste Site Cleanup

cc: Carol Comelison, Commissioner, Division of Capital Asset Management
Martin Suuberg, Regional Director, MassDEP-CERO
Mary Gardner, Deputy Regional Director, BWSC, MassDEP-CERO
Ms. Leslee Willets, Conservation Agent, Medfield Conservation Commission
Mr. Michael Sullivan, Town of Medfield Administrator
Mr. John Thompson, LSP, SHERC Chairman
Ms. Margaret Van Deusen, Director, Charles River Watershed Association
Ms. Andrea Stiller, LSP, ADS Environmental Engineering, LLC
Mr. Frank Ricciardi, LSP, Weston and Sampson, Inc.
Mr. William Massaro, PIP Petitioner
PIP Repository, Town of Medfield Public Library
CERO File:Database

Bill Massaro’s Letter Today on MSH Clean Up Status

William J. Massaro, Medfield, MA

 1 August 2011                                                                                                       Page 1 of 7

 The Commonwealth of Massachusetts

Division of Capital Asset Management

 One Ashburton Place, 15th Floor

 Boston, MA 02108

Attention:  Mr. Allen Wiggin

Re:  Former Medfield State Hospital C&D Area Draft IRA–RTN 2-3020799 and

Related Permit/Approval Applications

Dear Mr. Wiggin,

This letter is written to express my comments and concerns regarding the current submittals made by the Massachusetts Division of Capital Asset Management (DCAM) and their consultants Weston & Sampson Engineers, Inc. and Rackemann Strategic Consulting, Inc. to Federal, State and local agencies.

These submittals request approval/permitting of the cleanup of the Construction and Demolition Debris (C&D) Area and adjacent sediments in the Charles River at the site of the former Medfield State Hospital (MSH) and include:  a Notice of Intent filed 2 June 2011 with the Medfield Conservation Commission; a Category II General Permit with the U.S. Army Corps of Engineers filed 8 June 2011; a Notice of Project Change-EAA#14448R filed 15 June 2011 with MEPA; and a 401 Water Quality Certification Request filed with DEP-DWW on 22 July 2011.

In addition to the above submissions, this letter also addresses comments and concerns to the Draft Immediate Response Action-C&D Area RTN 2-3020799 which was presented to the Medfield PIP group on 14 July 2011 for comment on or before 3 August 2011.

Comments and Concerns

A. Background -My Initial Involvement and Concerns 

    

1. My Involvement

I am a thirty-five year resident of Medfield and abutter of the former MSH property.  My interest and concern with the hazardous material contamination and proposed cleanup of the property began in July of 2009 with DCAM’s original MEPA submittal of ENF 14448 for cleanup activity at the C&D Area site.  I had recently attended a DCAM presentation on the proposed redevelopment of the property which described housing for approximately one thousand adults and children, and the planned recreational use of the Charles riverside area by

these future residents and the general public. This recreational use was to include hiking and equestrian trails, and kayak/canoe launching facilities.

1 August 2011

W. Massaro

p. 2 of 7

In researching the DEP database for my response to this ENF, I found reports from TRC Environmental in 2003 which had estimated, after limited subsurface investigation of the entire MSH property, that the extent of contamination for this C&D site was a “minimum” of 150 feet by 400 feet or 60,000 square feet and a volume of 27,700 cubic yards. Subsequent reports by Maguire Group Inc. in 2005 and 2007 stated that their investigations were conducted only at previously investigated central and eastern portions of the Site, and simply reiterated TRC’s prior “minimum” size estimate.

These reports led me to conclude that the proposed plan did not appear adequate to protect the adults and children who would make recreational use of the area. In particular I was concerned by statements in the prior reports that, since investigations had only been conducted at central and eastern portions of the site, the extent and nature of contamination had not yet been adequately defined.

2. Initial Concerns

      

a. Inadequate Determination of Nature and Extent of Contamination

The 2009  proposed ENF activity did not address extending size investigations, and also did not address statements about potential/suspect asbestos found in test pitting, levels of lead up to 21 times in excess of standard due to coal ash and incineration waste dumping, and high levels of arsenic, barium, chromium lead and zinc in sediment.

In my letter to then Office of Energy and Environmental Affairs Secretary Bowles,

I stated that I believed more extensive efforts were required to achieve a “condition of no significant risk”.

b. Risk to Future Recreational User Not Addressed

The 2009 proposed ENF activity did not discuss current and proposed recreational utilization of the C&D Area and did not address mitigation of contaminant exposure risks to the hikers, fishermen, and others who would be using this area.

c. Segmentation

 

In addition to the issue of inadequate definition of the nature and extent of contamination, other members of the public, Medfield Town officials, and I expressed concerns that the ENF did not take into account the planned development of 440 housing units, the addition of a thousand adult and child residents, and their expected use of the property.

d. PIP Process Problems

Subsequent to the submittal of these concerns and the formation of a new PIP group for the Salvage Yard, on 31 December 2009 DCAM sought approval for a Special Project Designation (SPD) on the property.  This was to include the three MCP sites of the Salvage Yard, C&D Area, and the former power Plant Area.  Four non-MCP areas had been previously identified for investigation/cleanup but were not included in this SPD application.

1 August 2011

W. Massaro

p. 3 of 7

i. Progress Report Schedules

In my review of the draft SPD Statement of Work and in my 23 January 2010 comment letter to MassDEP CRO-BWSC regarding this SPD application, I stated that I was encouraged by DCAM’s confirmation of their intent to perform a “permanent comprehensive cleanup of the site and to achieve a condition of No Significant Risk” for future residents and recreational users of the property.   While I had no objection to the SPD, I did restate my prior concerns about the nature and extent of investigation in the C&D Area.   I also questioned the handicap that would be imposed on the PIP group as a result of the SPD’s proposed plan for release of Progress Reports only at six-month intervals.

ii. Timeliness of Investigation/Analysis Data Releases

 

Given the public response deadlines under the PIP process, and the size and complexity of the SPD comprehensive effort and its anticipated large volume of laboratory analysis results, I questioned whether the release of data to the PIP group in large six-month batches allowed for our reasonable review/identification of any issues or gaps in the data provided.  I questioned the likelihood that any resultant requests for additional investigations or analyses efforts would be incorporated in work likely to have been long-since completed.

My suggestion that information, assessments and determinations should, instead, be made available and distributed as they became available was not accepted.

On 25 March the SPD was granted.  Shortly thereafter DCAM sought and, despite concerns from the combined PIP groups and Medfield Selectmen urging a two-phase Environmental Impact Report, received MEPA approval of a Single EIR for the entire former MSH redevelopment project, including MCP, non-MCP and future building demolition/renovation activities under an Expanded ENF 14448.

B. Current Issues/Concerns 

The Phase II Comprehensive Site Assessment is not complete.  A premature and perhaps inadequate or inappropriate alternative remediation is being expeditiously pursued via the proposed IRA plan despite DCAM’s statement in Section 2 of their 1 February 2010 EENF application to MEPA  that  “Prior to evaluating remedial alternatives and selection of an applicable and appropriate alternative for the proposed end use, a Phase II Comprehensive Site Assessment(CSA) as defined under the MCP will be completed to evaluate the extent of impacts and the level of risk posed by the site…”

Today, almost 2 years after my initial involvement, I am concerned that DCAM, in spite of the public’s long-stated and often-repeated concerns that the boundary of the C&D Area may still not be adequately defined and that contaminant investigation on the riverbank, wetlands and in the river is not yet complete, has not provided data to support their position that historic “minimum” estimates were accurate and complete.

1 August 2011

W. Massaro

p. 4 of 7

I am again concerned about what may well be a return to segmentation and a to remediation effort which results in something less than the promised “Comprehensive” cleanup.

I am concerned, by what I believe to be the current diminution of the effectiveness of the PIP process in Medfield by this rush to obtain permitting agency approvals and implement the proposed C&D Area IRA.  Work will have begun and likely be completed before the Town of Medfield, the PIP group, and other concerned parties even receive data crucial for a reasonable and prudent evaluation of remediation alternatives.

I am concerned that elements of the MCP five-phased process may be circumvented or rendered moot.

1. Phase II Status and Pending Proposed Completion

  

a. Size of the C&D Area

As described above the size of this area had been originally estimated at a “minimum” in 2003, and despite  repeated Town and public requests for further investigation remained essentially unchanged until the 14 July 2011 Draft C&D IRA presentation.  At this presentation Weston & Sampson reported it had been increased to 3.2 acres.   Upon further questioning it was learned this increase was attributed to the addition of 5 debris piles (shown on several earlier sits maps as adjacent but not within the prior boundary definition) and to the inclusion of the 800 square feet of river bottom described in the IRA.

In response to questioning as to whether any sampling had been performed in the wetland outside of the prior boundaries and whether clean limits had been obtained, Weston and Sampson advised that results would be included in the Final Phase II report scheduled for release in September.

This data may or may not confirm that the true boundaries of the construction and demolition debris deposits have finally been identified.  However, because the current proposed IRA implementation is scheduled to begin before this information is released, the opportunity for concerned parties to effectively utilize this data to evaluate whether the proposed IRA is appropriate and adequate will have been lost.

b.CVOC Investigation Still Incomplete

In the fall of 2010 a chlorinated solvent plume was found migrating toward the Charles River.  Concerns about its proximity within the Zone II to Town Well #6, our principal water supply, and its location within a Potentially Productive medium Yield Aquifer prompted the PIP group and Town officials to request additional monitoring well installations and analyses.  Results of any additional sampling are not expected to be made available until release of the Phase II Final report.

1 August 2011

W. Massaro

p. 5 of 7

The proposed IRA does not address the effect of its implementation on existing wells in the area or address the probability that future wells may be required to monitor and/or remediate effect of the CVOC contamination. I believe that clear delineation of the plume and preparation of remediation alternatives for both the C&D contaminants and the CVOC Plume should be complete before implementation of the IRA, and it should be established that the remediation of the CVOC’s will not be hindered or impeded by C&D IRA activity.

c. New Sediment Samples and Analyses Not Released

Neither locations nor analytical results of iterative sediment samples which have been taken in the river and adjoining wetlands since issuance of the Interim Draft CSA Report have been released.  This data and that pertaining to any new sampling/analyses will not be available for public review until release of the Phase II CSA Final Report.

d. C&D and Power Plant Areas Are Not Severable

 

i. Shared Contaminants

There are many very large areas of fill consisting of coal ash and incineration waste generated by boilers in the former Power Plant area before their conversion from coal to fuel oil.  This material was deposited over decades in the Power Plant area and in the C&D area.  At least one of these deposits runs from one Release Area into the other. Constituents of these deposits are the same.  As part of the permanent comprehensive solution promised by DCAM under the SPD, the C&D Area remediation should not be separated from the Power Plant Area.

ii Shared Current & Proposed Uses

The Bay Circuit Alliance’s Charles River Link Trail currently uses sections of both the C&D and Power Plant Areas. Their 16 March EENF#1448 letter to then Secretary Bowles stated their concern that current use and access to these areas be maintained: “We request …development of the area take into consideration the need to continue access for the Charles River Link Trail.”   Regarding planned future use of the areas, the Alliance stated that “We are in favor of the proposed future canoe landing located at the Construction Debris Area along the Charles.  It will provide not only access to the river but better public access to the Medfield State Forest.”

e. Impact on Recreational Use of the C&D Area

I am concerned that the proposed IRA remediation will not comply with the statements that DCAM made in their February 2010 EENF submittal that “Due to this [disposal area being near to the redevelopment parcel–may become play area for children from the new housing areas], Conceptual Site Models for the Power Plant Area and the C&D Area will recognize potential uses that may be more intrusive than passive recreation”.

The expedient solution proposed may well leave contaminants in the area and put recreational users at an unacceptable level of exposure risk.

1 August 2011

W. Massaro

p. 6 of 7

2. PIP Process-Should Not be a “Rubber Stamp”

As described in the opening paragraph of this letter, DCAM and/or their consultants began seeking multi-agency approvals of the C&D Area IRA remediation well in advance of presenting it to the Medfield PIP group.

Given the 3 August 2011 requirement for submittal of PIP comments/concerns about the current IRA and given the time allowed for DCAM responses, it is likely that most, if not all,                                                                                             of the requested permitting/approval actions by these agencies could be completed before the PIP group even receives DCAM’s answers.   This would mean, in effect, that agencies might approve fragments of plans and proposals even while public comments are being solicited.  It would seem highly unlikely that any subsequent incorporation of public comments by DCAM would occur after one of these approvals has been granted.  The Town and the PIP group will, in effect, have been presented with a fait accompli.

 

3. MCP Issues

 

a. Out of Sequence Phases

 

The C&D Area is clearly the most challenging of the disposal sites in the SPD and its contaminants are inseparable from those in the contiguous Power Plant Area.    I am concerned that any such de facto advance approval of the C&D Area IRA’s proposed solution will  circumvent the MCP-mandated requirement to submit detailed Phase III Identification and Evaluation of Remedial Action Alternatives for what is effectively the entire SPD.

A premature approval of the proposed IRA plan before completion of the Phase II CSA would in effect leap-frog Phase III.  By the time Phase II is completed, the C&D Area and the majority of the SPD will, in effect, have completed Phase IV remediation and landed in Phase V.

b. Inappropriate “Temporary” Solution Will Become Permanent

 

The premature clearing and capping of the proposed riverbank and the capping of the proposed section of river sediment may be found to be inappropriate or inadequate upon completion of the Phase II CSA. It is not unreasonable to assume that in preparation of Phase III alternatives, DCAM will include the cost of removing these “temporary” remediations which will become a significant added cost element in their recommendation for Phase IV.

To the continuing detriment of the river ecology, risk to the Town’s water supply, and the exposure of recreational users, it is most likely that the “temporary” solution will become the “permanent” solution.

1 August 2011

W. Massaro

p. 7 of 7

Conclusion

 

As a long-time resident of Medfield, abutter of the former MSH property, member of the Medfield PIP, and a recreational user of the Charles River, I hope that I have presented sufficient detail regarding my concerns with the C&D IRA proposal.

I hope I have demonstrated that at this time, agency approval/permitting before public release of the Final Phase II Comprehensive Site Analysis and  Phase III Alternatives is at best premature, and in the final analysis  may be neither adequate nor appropriate.

Thank you for this opportunity to present my comments and concerns on this important issue.

Yours truly,

William J. Massaro

 

Addressees:  Mr. Richard K. Sullivan, Executive Office of Energy and Environmental Affairs, Boston, MA

  District Engineer U.S. Army Corps of Engineers Regulatory Division, Concord, MA

  Ms. Stella Tamul, DEP Water, Wastewater & Wetlands- CRO, Worcester, MA

  Mr. Allen Wiggin, Division of Capital Asset Management, Boston, MA

  Ms. Leslee Willitts, Conservation Commission, Medfield, MA

CC:                Rep. Stephen F. Lynch, Boston MA

Sen. James E. Timility, Boston, MA

Rep. Denise C. Garlick, Boston, MA

Rep. Daniel B. Winslow, Boston MA

Ms. Carole Cornelison, Mass Division of Capital Asset Management

Mr. John O’Donnell, Mass Division of Capital Asset Management

Mr. Mark Baldi, Mass DEP CRO-BWSC

Mr. Frank Ricciardi, Weston & Sampson

Ms. Elise Leduc, Charles River Watershed Association

Medfield Town Administration (M. Sullivan, K. Trierweiler)

Medfield Town Selectmen (O. Peterson, A. Thompson, M. Fisher)

Medfield State Hospital Environmental Review Committee

Westborough mulls buying state hospital property – Framingham, MA – The MetroWest Daily News

Westborough mulls buying state hospital property – Framingham, MA – The MetroWest Daily News

http://www.metrowestdailynews.com/news/x633531002/Westborough-mulls-buying-state-hospital-property

DCAM to Convene Working Group with Town

DCAM Commissioner Cornelison has yet again been good to her word to work collaboratively with the Town of Medfield on the clean up of the Medfield State Hospital site.  At my suggestion (borrowing Billl Massaro’s idea), she has agreed to convene a working group to discuss the environmental issues, where the current PIP and others processes are too overly formalistic to get to fast answers and to allow input by the town.  Medfield will be represented on  the working group by the chair of the State Hospital Environmental Review Committee (SHERC) and the two town administrators.  This morning the first meeting still had not been scheduled, but it should take place this week.

Medfield State Hospital – DCAM’s Proposal to ConCom for an Immediate Response Action

After consulting with an expert, SHERC chair, John Thompson, on the environmental clean up of the Medfield State Hospital site DCAM proposes to the Conservation Commission, I suggest that DCAM alter its proposal so as to conform to the best interests of both the Town of Medfield and the general public.

1.    The oil in the Charles River should be removed, not just capped, and
2.    The C & D area should be excavated so that the fill there is no longer in contact with groundwater (instead of being capped in place).  The fill does not need to be taken off-site, as a capped on-site area could be designed parallel with the topographic contours along the gas line. The goal should be to keep the fill above the water table and away from the flood plain.

The town’s concern is that the C & D area is (1) adjacent to the area from which the town’s well #6 draws water, and (2) the land beneath the C & D area is considered as a “potentially productive aquifer,” which could be used for future water supply purposes.  However, if the C & D area is capped with the currently proposed temporary measure, I am told that it is unlikely that the land could ever get permitted for any water supply use.  Therefore leaving the fill below the water table is a bad idea.

Oleana Foundation – College Propsed for Medfield State Hospital Site

I met this afternoon with Vincent Rocchio and Eric Terzuolo of the Oleana Foundation, who are looking to site a new liberal arts college and 100 units of elderly housing at the Medfield State Hospital site.

Their idea =
1.    Liberal arts college for 1,000 students at the Medfield State Hospital site
a.    $10,000 per year tuition, room and board
b.    Professors live at site and contribute to running the place
c.    Few administrators
2.    100 units of housing for the elderly at the site

Looking for collaboration with the Town of Medfield
1.    Use and contribute to the Medfield High School library
2.    Have Medfield Police Department provide security at their college
3.    Share bulk purchasing with the Town of Medfield and its schools

The three selling points of their concept =
4.    Innovative
5.    Access
6.    Green

Financial
7.    They feel there is grant money available for the uses they propose, particularly in the manner in which they propose it
a.    e.g. – green renovation of college buildings