Revised schedule of upcoming projects
Attached is a revised schedule of upcoming projects. Donna could you post this on the web site? Thanks. Mike [Sullivan]
June 23 and 24 – DPW to remove excess fill from High School field in conjunction with field and track reconstruction
June 27 through July 15 – grinding and paving of Green Street and North Meadows Road from West Street to the Charles River.
Friday June 24 – activate electric service to new Hospital Road water tower
Week of June 27th – complete sterilization of new water tower and fill
No date established yet – removal of old hospital water tower
Week of June 27 – start replacement of South Street gas main from Pound Street to Philip Street
Sunday, June 26th 9:00 a.m. to 4:00 p.m. – Car show at former state hospital site.