DCAM granted the town a 20 day extension to respond


Emailed extension from DCAM last night for town’s time to respond to DCAM’s Phase II and III remediation materials – permitting to proceed –

From: Duran, Sandra (DCP)

Sent: Tuesday, April 03, 2012 9:41 PM
To: Kristine Trierweiler
Cc: Wiggin, Allen (DCP); O’Donnell, John (DCP)
Subject: RE: Meetings and Extension Request for Phase II/Phase III

Ms. Trierweiler:

DCAM intends to proceed with its planned PIP and permitting efforts as we are trying to keep the work on track for implementation this summer.  As such, we have scheduled our next PIP meeting with the Town on April 12, 2012 from 7-9pm.  At this meeting, we plan to present the Phase IV Remedy Implementation Plan to the community.  This plan will speak to the specific construction design aspects of the currently proposed remediation effort.

On March 27, 2012, the Town of Medfield requested a 20-day extension to the public comment period of Draft Final Phase II Comprehensive Site Assessment and Draft Final Phase III Alternative Analysis MCP Documents.  These documents were provided to the Town on March 15, 2012 (presented on March 22, 2012).  We have considered the Town’s request.

Please be advised that we will grant the Town the requested 20-day extension request; however, we will file the various permit applications simultaneously with the circulation of the Phase IV and the requested PIP extension.  Those permit proceedings would run on a parallel track with the Phase IV PIP Comment period.  If  those Phase IV comments warrant revisions to the permit applications, those revisions can be made for each application as needed.  All permit proceedings would still be open beyond the Phase IV comment deadline.

Please let me know if you have any questions or comments regarding the above matter.

Sandra

Sandra R. Duran

Director of Building Maintenance and Operations

The Commonwealth of Massachusetts

Division of Capital Asset Management