| With the heavy rains, the Waste Water Treatment Plant had some issues. Both EPA and DEP have signed off on the temporary corrective measures. |

TOWN OF MEDFIELD
MASSACHUSETTS
“Department of Public Works
MAURICE G. GOULET
Director of Public Works
55 North Meadows Road
Medfield, MA 02052
(508)359-8597
Fax (508) 359-4050
TO: Board of Selectmen
Michael Sullivan, Town Administrator
Kristine Trierweiler, Assistant Town Administrator
Water and Sewer Board
FROM: Maurice G. Goulet. Director of Public Works
MEMORANDUM
DATE: April 4, 2017
SUBJECT: WWTP Issue
We experienced an influx of water at the Wastewater Treatment Plant due to excessive rains. This influx of water forced us to bypass partial treatment areas at the plant. The UV Control System at the end of the treatment areas is in need of repair. A temporary chlorine tank and feed has been set up at the final stage of treatment for disinfection. This chlorine tank is necessary for the interim until the UV Control System can be repaired and put back on-line. New controls and repair parts have been ordered and will be installed as soon as possible. When the UV Control System is running properly, the chlorine tank and feed will be removed.