The three bids that were received for the new water tower next to the old water tower at the former Medfield State Hospital site were opened on Wednesday, and reported to the Water & Sewer Board last night. Per the emails from the town’s consulting engineer and Mike Sullivan, copies appear below, the low bid was $3,064,933 The other two bids were $3.286m. and $3.67m.
Bid tabulation for state hospital water tower attached for your information. Bids were opened at 3:00 p.m. Wednesday. Water & Sewer Board is meeting tonight (7:00 p.m., Warrant Committee room) to review bids and receive recommendations from its engineer/consultant, Environmental Partners. Please do not post this until Water & Sewer Board has had a chance to review. Thanks Mike
From: “Paul C. Millett”
Sent: Wednesday, August 20, 2014 8:52 PM
Subject: Bid Tabulation – Medfield Hospital Tank Replacement – 8-20-14.pdf
Folks:
Favorable bids were received this afternoon.
The apparent low bid of just over $3m was from Phoenix Fabricators. The engineer’s estimate was $3.3M.
I will bring a summary to tomorrow evening’s meeting and an overall total project budget update.